Summary
In July 1984, Hdro Electric Project (HEP) Orginisation of WAPDA prepared a draft feasibility report of Kargah Hydro Electric Station Phase VI. This report based on reconnaisance level studies presented broad concept for Phase VI scheme in continuation of the first V Phases already developed by Norther Area Works Organisation (NAWO). The concept was that:- a) A gross head of 713 feet exists between the tailrace of upper most Phase V Power Station and the next Phase II. b) At present only 300 feet of this head is being utilized for generation with maximum discharge of 26 cusecs. c) Phase VI Scheme envisages effective utilization of this total head and surplus flows of Kargah nallah for generation of 3 MW power.(LB)