Engineering service for flood protection of pat Feeder & Kirthar canal (Baluchistan portion): Progress report for the period ending May 31, 1979
Bibliographic details
Summary
The overall progress ending May 31, 1979 is estimated at 26% against 25% stipulated. Progress on Major items of work are detalied in Attachment-I. The staff fully mobilized is busy in preperation of schemes for immediate remedial measures for flood protection of Pat feeder and Kirthar canal (baluchistan Portion).