Dewatering Plan of Nangar Nai Project, Dera Ghazi Khan

By Kazi Mujib Ashraf

Bibliographic details

Summary

On the request of Project Manager BC-1 project Pakistan Atomic Energy Commission, Dera Ghazi Khan a tentative dewatering plan for Nangar Nai, D.G.Khan project has been proposed in this report. The report also includes the findings of an aquifer test of 240 hours pumping duration performed at Nangar Nai site. Fourteen tubewells have been proposed for dewaering the project area. All the tubewells are to be run continously at recommended discharge during the entire construction period fo the shaft and should be run at leat one month before the commencement of construction of shaft.