PakCat catalogue record

Sibi Jhatpat Development, Project Planning Report Nari Project Feasibility Report, 1966 Volume Vol.2

Bibliographic details

Summary

The purposal for the Nari Project is to store flood water by means of two dams at Badar Kach which can be operated so that sediment deposition in the main reservoir is reduced to the minimum. Badar Kach Dam will provide the main impounding reservoir, while Beji Diversion dam wll divert the flow of the Beji river (Two-thirds of the total) into the main reservoir when mecessary. The water supply to Upper nari is to be kept at its present quantity, and 19,000 acres cultivated at 160% intensity. The reminder of the water will irrigate a new development area of virgin land (Middle Nari, 13,000 acres) also at 160% intensity, and 90,000 acres in Lower nari at 110% intensity when reservoir supplied are good, the area cropped being reduced if there is less water. Heavy pre-watering is proposed for all crops to leach down the salts, as with the present flood irrigation.