PakCat catalogue record

PC-I Proforma and Project Estimate of Checking River Erosion D/S Taunsa Barrage to Project Mogasson Branch Cost Rs.17.31 Millions

Bibliographic details

Summary

The work is proposed to be taken up with the river diversion operation at Ghazi Ghat Bridge. The design and drawing of 2-J spurs is the same as given in Report NO.811 Fig:10.10. The work is required to be completed before the advent of coming flood season, it is therefore, proposed to get the earthwork completed with the earthwork machinery and the same rates have therefore been provided in the estimate. The other items of work are of D.S.R. and necessary references have also been indicated against each item. The work of Language Chap is essential for carrying out the work under water for which necessary analysis of rates has been prepared to support its cost.(LB)