Dina Irrigation Project: Feasibility Report 1975

Bibliographic details

Summary

Dina irrigation project proposes to provide irrigation facilities to 8,000 acres of culturable commanded area on the right side of river Jhelum between Mangla headworks of upper Jhelum canal and the railway line running between Karachi and Peshawar. Irrigation has been planned through 24 tubewells of two cusecs capacity each at an ultimate annual irrigation intensity of 150 per cent (60.90) Kharif: Rabi). The total cost of the project inclusive of interest during construction at 8.5 per cent has been estimated to Rs.118.28 Lacs (1975 price index). No foreign exchange is involved. Annual cost operation, maintenance and energy charges would be Rs.7.76 Lacs. Benefit Cost (B.C) ratio at 8 per cent interest rate comes to be 2.663: 1. The project is, therefore, technically feasible and economically viable and is recommended for early implementation.