Hydrologic Monitoring and Tubewell Performance in Larkana Tubewell Pilot Project 1977-78

Bibliographic details

Summary

The salinet conclusions derived from the analysis presented in the report are:- ; 1. Average working of 27 irrigation cum drainage tubewells and 8 drainage tubewells during the year was only 4 hours and 6 hours per day respectively against the recommended working of 10 and 14 hours per day. ; 2. The average groundwater level is merely 2.8 feet below general ground level during October as against planned level of about 7 ft below ground level ; 3. Insignificant lowering of watertable is due to low pumpage. ; 4. The pumping capacity of the project tubewells has decreased by about 9 percent since acceptance but this capacity is still nto below its designed. ; 5. The median value of specific capacities of tubewells has decreased by about 9 percent since acceptance. ; 6. None of the project tubewells was found to have any sand blowing problem. ; 7. Wire to water efficiency of tubewells ranges from 34 to 52 percent.