Hydrologic Monitoring and Tubewell Performance in Sukkuar Tubewells Pilot Project 1979

Bibliographic details

Summary

Conclusions: The salient conclusions derived from the analysis presented in the report are:- ; 1. Average groundwater level is about 7 feet below ground level during the month of October and it goes down to about 16 feet below ground level during the month of April. ; 2. The pumping capacity of the project tubewells has decreased by about 13 per cent since acceptance. ; 3. The median value of specific capacities of tubewells has decreased by about 6 per cent since acceptance. ; 4. Out of the total 18 tubewells, 4 tubewells were found to have sand contents of more than 50 ppm at the start of the pumping. ; 5. Wire to water afficiency of tubewells ranges between 33 and 49 per cent.