Monthly Progress Report on Hydraulic Model Studies, 1962

Bibliographic details

Summary

There were sufficient supplies in U.C.C. to run all the models at Nandipur simaltaneously. Model of diversion tunnels Mangla Dam was run almost round the clock. Upto about 85 percent work on circulation system for trays on the triangular portion between Gujranwala Daska Road and Upper Chenab Canal was completed in this month. the circulation system for Geometrical model of Marala Headworks was put into operation in the closing days of the month and the model was run for low discharges. Good progress continued on the moddel of Mangla Dam in laboratories at Lahore and satisfactory solution for energy dissipation with 5 tunnels and 10 bends was found out for schemes entailing the extension of power house to enclose 3 sets and 4 sets of turbines.