Review of Ongoing and high Priority Irrigation & Drainage Projects Second Interim report for the Preparation of Revised Action Programme & Perspective plan, Vol.3 Appendices B,C,D & E, 1977
Bibliographic details
Summary
In accordance with the Agreement, the second Interim Report is to include: i) Comprehesive review of on-going projects. ii) analysis and indentification of high-priority projects, iii) preparation of a programe of implementation for high-priority projects to be started during the first three years of the Fifth Plan period. Volume III. Contains five Appendice covering project description, project costs and project benefits in addition covering project description in addition to the description of the two computer models, which are utilized for economic analysis of the project are for simulation of the irrigation system.(LB)