Sediment Concentration at the Boil of Upper Chenab Canal and M.R. Link at Marala Headworks during the Period Oct, 68 to Sept, 69
Bibliographic details
Summary
This report contains the results of sediment concentration at the boil of Upper Chenab Canal and M.R. Link at Marala Headworks. The average daily concentration for upper chenab canal ranges between 228 PPM and 923 PPM and for M.R.Link the range is 381 PPM and 1045 PPM for the observed period. Total monthly river discharge is maximum monthly discharge is 3,71,110 A.ft. which occurs during December, 1960.(LB)