Critical Investigation of Stresses with Respect to First Phase to Clear Pole of Circuit Breaker 'Source Title' Mehran University Research Journal of Engineering and Technology Volume Vol.9, No.4
Bibliographic details
Summary
This paper discusses the breaking ability of a circuit breaker when its first phase to clear position is viewed while the contracts of other two phases of the three phase circuit are still closed. How much the first phase to clear is stressed as comparison to other tow following the are extinction at current zero is a problem to be examined after developing techniques and applying them on one practical example selected for this purpose. This circuit selected for calculation is a three phase one and the fault applied is three- phase and three-phase to earth type very close to the neighbourhood of the circuit breaker.