Hydrologic Monitoring and Tubewell Performance in Larkana Tubewell Pilot Project 1978-79
Bibliographic details
Summary
The salient conclusions derived from the analysis presented in the report are: ; 1. The average groundwater level is morely 2.6 feet below general ground level during October and it goes down to about 7 feet below ground level in the month of April, although as per planned target the water level should go about 10 below ground level in October. ; 2. Average working of 27 irrigation-cum-drainage tubewells and 8 drainage tubewells during the year was only 5.7 hours and 5.3 hours per day respectively against the recommended working of 10 and 14 hours per day. ; 3. The pumping capacity of the project wells has decreased by about 13 per cent since acceptance. ; 4. The median value of specific capacities of tubewells has decreased by about 12 per cent since acceptance. ; 5. None of the project tubewells was found to have any sand blowing problem. ; 6. Wire to water efficiencies fo the tubewells range between 33 and 51 per cent.