Performance Study of Tubewells on the Right Bank of Indus River in Dera Ismail Khan Area
Bibliographic details
Summary
Two schemes were undertaken for installing of tubewells in Dera Ismail Khan area. The first scheme was started in the year 1958 and completed by 1959. Since then sixty tubewells are in operation. Another scheme of thirty tubewells was undertaken in the year 1962 and so far twenty four tubewells have been installed, twenty three of which are in operation. In the year 1962 a survey of the performance of sixty tubewells of Scheme No.1 was conducted and the results were reported in a special Report No.239/Ph-T-W.-57/62. in October 1967, a performance survey was carried out for the tubewells of both these schemes. In this report complete information about these tubewell and their performance is putforth.(LB)