Pehur Scarp PC-1 Proforma, 1987
Bibliographic details
Summary
Frequent surface flooding and the recharge from Pehur canal throughout the project area has not only caused constant rising of ground water table but also brought most of the area in the grip of sereve waterlogging. Due to high silting/Blockage, the natural khwars/Drains and man made drains in the area have become incapable of taking the designed surface run off. The main constraint is therefore improper surface run off disposal system. The main objective of the scheme is remodelling of 3 Nos; Natural and artificial drains already existing in the area (55.4 miles in length). These drains in the area are not enough for taking surface run off, therefore a N0. of new drains (15.6 miles) are also to be constructed in the area. The project on completion will help increasing the cropping intensity from the present 93% to 150% thereby incresing the present cropped acreage from 43,222 acres to 69,717 acres.