Flood Protection of Pat Feeder & Kirthar Canal (M): Monthly Progress Report ending November 30, 1979
Bibliographic details
Summary
The overall progress upto November 30, 1979 is estimated at 72 percent against 84 percent stipulated. The progress has been showing declining trend since September 1979. This is due to physical constraints in field surveys and availability of technical data. The matter has been taken up with Government of Baluchistan. The same situation is still prevailing.(LB)